We create atmosphere for art and entertainment!

Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction

# type: Lower and upper stage machinery design and construction
# location: Szolnoki Szigligeti Színház - Szolnok, HU
Project

The Szolnok Szigligeti Theatre is one of the most prominent theatres in Hungary. The theatre opened its doors in 1912 and has been operating ever since.

During the project, a complete renovation of the Szolnok Szigligeti Theatre was carried out; as part of this, we were tasked with the design and construction of the entire lower and upper stage machinery.

Challenge

The design of theatre engineering equipment was a challenge in several ways.

On the one hand, they operate in the immediate environment of people, they might even move people, while on the other hand, they connect to an architectural environment.

Connections to buildings always force the designer to compromise. This was no different for the Szolnok Szigligeti Theatre. We had to adapt to the existing building structure and geometric conditions, both in the design and in the construction of theatre engineering equipment.

We were only able to place the machine units, control cabinets of the upper stage machinery on the existing fly system in the stage space.

We had to implement theatre technology control according to the highest safety standards.

Solution

We built 2 closed, acoustically sized housings on the existing fly system to accommodate the machine units and control cabinets of the upper stage machinery.

Due to the closed machine housing, we also installed air conditioning equipment to ensure the correct operating temperature.

The control has been awarded the highest available Safety Integrity Level 3 certification. The certification also applies to the safety PLC system and redundant PLC control.

*SIL3 certification and the associated sensors and endpoints are responsible for avoiding failures while protecting human life.

During the investment, the following machine units and stage technology elements were manufactured and installed:

► Machine-operated main stage fire compartmentation iron curtain equipment.

► Machine-operated side stage fire compartmentation equipment.

► Machine-operated electric lighting bridge system built into the stage space.

► Counterweight manual fly equipment (18 pieces).

► Greek system electric curtain track equipment.

► Machine-operated electric Bayreuthian equipment.

► Machine-operated power puller equipment (44 pieces).

► Machine-operated fly system equipment (18 pieces).

► Machine-operated lighting bridge equipment.

► Machine-operated lighting support equipment (2 pieces).

► Machine-operated panoramic support equipment.

► Machine-operated revolving stage equipment.

► Machine-operated personal lowering equipment (2 pieces).

► Machine-operated orchestra pit lowering equipment.

► Machine-operated furniture lifting equipment.

► Machine-operated chandelier lifting equipment.

► Machine-operated chain hoist equipment (4 pieces).

► Remote controlled motor stage trolley (4 pieces)

► Complete SIL3 stage technology control.

► Complete stage curtain system..

► Complete stage flooring.

► Project location: Szolnok Szigligeti Theatre

Address: 5000 Szolnok, Táncsics Mihály utca 20., Hungary

► Technological description *Safety Integrity Level (SIL)

In order to ensure that a system does not become dangerous to people and the environment in an emergency, operational safety requires systematic planning. SIL specifications are therefore key criteria for equipment manufacturing.

SIL stands for Safety Integrity Level.

SIL is an international measure used to classify the operational safety of a system.

There are three such levels in theatre technology, ranging from SIL1 to SIL3, the latter of which requires the most stringent measures due to the greatest risk.

In particular, this means that from the probabilities of failure of the components it creates accurate risk assessment, takes measures to minimize the residual risks, selects the appropriate tools and, finally, ensures the correct compliance of the SIL functions by means of repeated checks.

The photos were taken with a SAMSUNG Galaxy S21 FE 5G smartphone.

Project categories
Theatre play
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 1
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 2
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 3
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 4
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 5
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 6
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 7
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 8
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 9
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 10
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 11
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 12
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 13
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 14
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 15
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 16
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 17
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 18
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 19
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 20
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 21
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 22
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 23
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 24
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 25
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 26
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 27
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 28
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 29
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 30
Szolnok Szigligeti Theatre Complete Theatre Engineering Reconstruction 31
Background Image
Background Image
More projects
Balatonfüred Congress Centre - Complete stage technology design and construction

A four-season congress centre has been constructed in Balatonfüred; during the erection of the congress centre we performed the entire stage technology design and construction.

Project details
HUNGEXPO REBORN - GALA SYSTEMS / Gala Venue system construction

In the framework of the HUNGEXPO reconstruction the plenary chamber of the CK building received a Gala Venue event-specific reconfigurable hall. The transformable hall contains a total of 8 preset positions. The operators may set up other unique p...

Project details
Background Image